Description
1 - To develop tools and methodologies for risk assessments of climate related impacts 3- To evaluate new and alternative approaches to address challenges in rail safety resulting from a changing climate.
Amendment chain · 2 entries
Each notch is one published row for this agreement: #0 is the original (placed at its start date) and each later notch is an amendment (placed at its amendment date). The height is the agreement's total value as of that row — the source column is cumulative, not a change amount — so the line reads as the commitment over time and the right-most notch is the current commitment shown in the header. For this agreement: $230,000 at start, $226,015 after amendment #1 (−$3,985).
- #02023-06-20$230,000
- #12024-08-30$226,015-$3,985
| Row | Date | Total value as of row | Change vs previous | Description on this row |
|---|---|---|---|---|
| #0 original | 2023-06-20(start date) | $230,000 | — | 1 - To develop tools and methodologies for risk assessments of climate related impacts 3- To evaluate new and… |
| #1 amendment | 2024-08-30 | $226,015 | −$3,985 | 1 - To develop tools and methodologies for risk assessments of climate related impacts 3- To evaluate new and… |
Related records · 11
Records are related by an explicit link in the data, stated for each group below — never by text similarity. Values are each agreement's current commitment (latest amendment).
Other current agreements for the same recipient (business number 100769694)
| Ref | Department · program | Current value | FY |
|---|---|---|---|
| 217-2024-2025-Q1-09702 | Transport Canada | Transports Canada · Rail Safety Improvement Program / Rail Safety Improvement Program: Infrastructure Technology and Research Component | $3,349,064 | FY2024 |
| 217-2023-2024-Q3-13445 | Transport Canada | Transports Canada · Rail Safety Improvement Program / Rail Safety Improvement Program: Infrastructure Technology and Research Component | $2,140,000 | FY2024 |
| 217-2023-2024-Q1-11412 | Transport Canada | Transports Canada · Rail Safety and Improvement Program / Rail Climate Change Adaptation Program | $300,000 | FY2024 |
| 217-2023-2024-Q2-04704 | Transport Canada | Transports Canada · Rail Safety and Improvement Program / Rail Climate Change Adaptation Program | $260,000 | FY2024 |
| 217-2022-2023-Q1-08188 | Transport Canada | Transports Canada · Rail Safety Improvement Program: Infrastructure Technology and Research Component | $1,877,539 | FY2023 |
| 217-2022-2023-Q1-08128 | Transport Canada | Transports Canada · Rail Safety and Improvement Program / Rail Safety Improvement Program: Infrastructure Technology and Research Component | $972,379 | FY2023 |
Other recipients funded under "Rail Safety Improvement Program / Rail Climate Change Adaptation Program" by Transport Canada | Transports Canada (most recent first)
| Ref | Recipient | Fiscal year | Current value | FY |
|---|---|---|---|---|
| 217-2023-2024-Q3-06037 | Tshiuetin Rail Transportation|Transport Ferroviaire Tshiuetin | FY2024 | $215,257 | FY2024 |
| 217-2023-2024-Q3-12487 | Tshiuetin Rail Transportation|Transport Ferroviaire Tshiuetin | FY2024 | $300,000 | FY2024 |
| 217-2023-2024-Q2-04961 | Great Western Rail Ltd.|Great Western Rail Ltd. | FY2024 | $249,409 | FY2024 |
| 217-2023-2024-Q2-04705 | 101115529 Saskatchewan LTD. o/a Last Mountain Railway|101115529 Saskatchewan LTD. o/a Last Mountain Railway | FY2024 | $241,177 | FY2024 |
| 217-2022-2023-Q4-11206 | Hudson Bay Railway Corporation|Hudson Bay Railway Corporation | FY2023 | $300,000 | FY2023 |
Cite as: Glassbox record view · Federal grants & contributions · 217-2023-2024-Q2-04960 · retrieved 2026-11-12.