Description
The objective of this Project is to advance predevelopment work for a “closed loop” pumped storage system in Alberta, utilizing the legacy footprint of a former mine's open pit as the upper reservoir supporting a larger energy storage proje…
Amendment chain · 1 entry
Each notch is one published row for this agreement: #0 is the original (placed at its start date) and each later notch is an amendment (placed at its amendment date). The height is the agreement's total value as of that row — the source column is cumulative, not a change amount — so the line reads as the commitment over time and the right-most notch is the current commitment shown in the header.
- #02025-02-11$1,320,476
| Row | Date | Total value as of row | Change vs previous | Description on this row |
|---|---|---|---|---|
| #0 original | 2025-02-11(start date) | $1,320,476 | — | The objective of this Project is to advance predevelopment work for a “closed loop” pumped storage system in A… |
Related records · 5
Records are related by an explicit link in the data, stated for each group below — never by text similarity. Values are each agreement's current commitment (latest amendment).
Other recipients funded under "Contributions in support of Electricity Pre-development Projects Program" by Natural Resources Canada | Ressources naturelles Canada (most recent first)
| Ref | Recipient | Fiscal year | Current value | FY |
|---|---|---|---|---|
| 115-2024-2025-Q4-16965 | EAC CAPITAL LIMITED PARTNERSHIP | FY2025 | $8,366,800 | FY2025 |
| 115-2024-2025-Q4-16262 | NEW BRUNSWICK POWER CORPORATION | FY2025 | $1,280,000 | FY2025 |
| 115-2024-2025-Q4-16261 | NEW BRUNSWICK POWER CORPORATION | FY2025 | $12,575,244 | FY2025 |
| 115-2024-2025-Q4-16255 | INDEPENDENT SYSTEM OPERATOR | FY2025 | $18,559,590 | FY2025 |
| 115-2024-2025-Q4-16181 | NOVA SCOTIA POWER INCORPORATED | FY2025 | $3,127,484 | FY2025 |