Description
This project aims to upgrade and renovate an acquired copper foil manufacturing facility in Granby, Quebec, to produce battery-grade copper foil for electric vehicle (EV) and energy storage systems (ESS). The project’s work phase is schedul…
Amendment chain · 2 entries
Each notch is one published row for this agreement: #0 is the original (placed at its start date) and each later notch is an amendment (placed at its amendment date). The height is the agreement's total value as of that row — the source column is cumulative, not a change amount — so the line reads as the commitment over time and the right-most notch is the current commitment shown in the header. For this agreement: $70,000,000 at start, $70,000,000 after amendment #1 (+$0).
- #02026-03-30$70,000,000
- #12026-06-30$70,000,000
| Row | Date | Total value as of row | Change vs previous | Description on this row |
|---|---|---|---|---|
| #0 original | 2026-03-30(start date) | $70,000,000 | — | This project aims to upgrade and renovate an acquired copper foil manufacturing facility in Granby, Quebec, to… |
| #1 amendment | 2026-06-30 | $70,000,000 | +$0 | This project aims to upgrade and renovate an acquired copper foil manufacturing facility in Granby, Quebec, to… |